[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126980":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1126980,792,2,"多选题","关于正、反循环钻孔，说法正确的有（）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","泥浆护壁成孔时根据泥浆补给情况控制钻进速度，保持钻机稳定",true,{"key":16,"text":17,"correct":14},"B","发生斜孔、塌孔和护筒周围冒浆、失稳等现象时，应停钻采取相应措施",{"key":19,"text":20,"correct":14},"C","达到设计深度，灌注混凝土之前，孔底沉渣厚度应符合设计要求",{"key":22,"text":23,"correct":24},"D","设计未要求时，端承型桩的沉渣厚度不应大于150mm",false,{"key":26,"text":27,"correct":14},"E","设计未要求时，摩擦型桩的沉渣厚度不应大于300mm","ABCE","P56-60 正、反循环钻孔： (1)泥浆护壁成孔时根据泥浆补给情况控制钻进速度：保持钻机稳定。 (2)钻进过程中如发生斜孔、塌孔和护筒周围冒浆、失稳等现象时，应先停钻，待采取相应措施后再进行钻进。 (3)钻孔达到设计深度，灌注混凝土之前，孔底沉渣厚度应符合设计要求。设计未要求时端承型桩的沉渣厚度不应大于100mm；摩擦型桩的沉渣厚度不应大于300mm。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]