[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126976":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1126976,792,2,"多选题","关于沉入桩施工技术要点，正确的有（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","沉桩时，桩锤、桩帽或送桩帽应和桩身在同一中心线上",true,{"key":16,"text":17,"correct":18},"B","桩身垂直度偏差不得超过1％",false,{"key":20,"text":21,"correct":14},"C","接桩可采用焊接、法兰连接或机械连接",{"key":23,"text":24,"correct":14},"D","终止锤击应以控制桩端设计标高为主，贯入度为辅",{"key":26,"text":27,"correct":14},"E","沉桩过程中应加强对邻近建筑物、地下管线等的观测、监护","ACDE","P56-60 沉入桩基础施工技术要点： (1)预制桩的接桩可采用焊接、法兰连接或机械连接，接桩材料工艺应符合规范要求。 (2)沉桩时，桩帽或送桩帽与桩周围间隙应为5~10mm；桩锤、桩帽或送桩帽应和桩身在同一中心线上；桩身垂直度偏差不得超过0.5%。 (3)沉桩顺序：对于密集桩群，自中间向两个方向或四周对称施打；根据基础的设计高程，宜先深后浅；根据桩的规格，宜先大后小，先长后短。 (4)施工中若锤击有困难时，可在管内助沉。 (5)桩终止锤击的控制应视桩端土质而定， 一般情况下以控制桩端设计标高为主，贯入度为辅。 (6)沉桩过程中应加强邻近建筑物、地下管线等的观测、监护。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]