[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126958":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1126958,792,2,"多选题","箱涵顶进前应检查验收( )，必须符合设计要求。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","箱涵主体结构的混凝土强度",true,{"key":16,"text":17,"correct":18},"B","后背施工",false,{"key":20,"text":21,"correct":18},"C","顶进设备液压系统安装及预顶试验",{"key":23,"text":24,"correct":18},"D","线路加固",{"key":26,"text":27,"correct":14},"E","箱涵防水层及保护层","AE","2021\u002F2020版教材P68 (二)箱涵顶进前检查工作(1)箱涵主体结构混凝土强度必须达到设计强度，防水层及保护层按设计完成。(2)顶进作业面包括路基下地下水位已降至基底下500mm以下，并宜避开雨期施工，若在雨期施工，必须做好防洪及防雨排水工作。(3)后背施工、线路加固达到施工方案要求；顶进设备及施工机械符合要求。(4)顶进设备液压系统安装及预顶试验结果符合要求。(5)工作坑内与顶进无关人员、材料、物品及设施撤出现场。(6)所穿越的线路管理部门的配合人员、抢修设备、通信器材准备完毕。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]