[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126951":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1126951,792,2,"多选题","关于移动模架法现浇预应力混凝土连续梁的要求，正确的有( )。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","模架长度必须满足施工要求",true,{"key":16,"text":17,"correct":14},"B","模架应利用专用设备组装，在施工时能确保质量和安全",{"key":19,"text":20,"correct":14},"C","内、外模板就位时，其平面尺寸、高程、预拱度的误差必须控制在容许范围内",{"key":22,"text":23,"correct":14},"D","预应力筋管道、钢筋、预埋件设置应符合规范规定和设计要求",{"key":25,"text":26,"correct":27},"E","浇筑分段工作缝，宜设在弯矩零点附近",false,"ABCD","2021\u002F2020版教材P65页 使用移动模架法现浇预应力混凝土连续梁时支架长度必须满足要求；支架应利用专有设备组装，在施工时能确保质量和安全；箱梁内、外模板就位时，尺寸，高程，预拱度误差必须满足容许范围之内；浇筑施工缝，必须放在弯矩零点处；混凝土内预应力筋管道、钢筋、预埋件设置符合规范规定和设计要求。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]