[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126948":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1126948,792,2,"多选题","现浇预应力混凝土连续梁，常用的施工方法有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","支架法",true,{"key":16,"text":17,"correct":18},"B","顶推法",false,{"key":20,"text":21,"correct":14},"C","移动模架法",{"key":23,"text":24,"correct":18},"D","悬臂拼装法",{"key":26,"text":27,"correct":14},"E","悬臂浇筑法","ACE","2021\u002F2020版教材P65 (一)支架法现浇预应力混凝土连续梁；(二)移动模架上浇筑预应力混凝土连续梁；二、悬臂浇筑法",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]