[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126945":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1126945,792,2,"多选题","安装构件前，支承结构和预埋件的()应符合设计要求且验收合格。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","尺寸",true,{"key":16,"text":17,"correct":18},"B","外形",false,{"key":20,"text":21,"correct":14},"C","标高",{"key":23,"text":24,"correct":18},"D","数量",{"key":26,"text":27,"correct":14},"E","平面位置","ACE","2021\u002F2020版教材P64 (3) 安装构件前，支承结构（墩台、盖梁等）的强度应符合设计要求，支承结构和 预埋件的尺寸、标高及平面位置应符合设计要求且验收合格。桥梁支座的安装质量应符合 要求，其规格、位置及标高应准确无误。墩台、盖梁、支座顶面清扫干净。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]