[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126941":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1126941,792,2,"多选题","关于柱式墩台施工要求，正确的有( )。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","墩台柱与承台基础接触面应凿毛处理，清除钢筋污锈",true,{"key":16,"text":17,"correct":14},"B","浇筑墩台柱混凝土时，应铺同配合比的水泥砂浆一层",{"key":19,"text":20,"correct":14},"C","柱身高度内有系梁连接时，系梁应与柱同步浇筑",{"key":22,"text":23,"correct":14},"D","V形墩柱混凝土应对称浇筑",{"key":25,"text":26,"correct":27},"E","分层浇筑时，接缝应按施工缝处理",false,"ABCD","2021\u002F2020版教材P61页 选项E错误，柱式墩台施工浇筑混凝土时，宜一次浇筑完成",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]