[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126932":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1126932,792,2,"多选题","在一个基坑内沉入多根桩时，下列有关打桩顺序的说法中，正确的有( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","根据基础的设计高程，宜先深后浅",true,{"key":16,"text":17,"correct":14},"B","密集群桩由中心向四边打",{"key":19,"text":20,"correct":21},"C","根据桩的规格，宜先小后大",false,{"key":23,"text":24,"correct":14},"D","根据桩的规格，宜先大后小",{"key":26,"text":27,"correct":21},"E","根据桩的规格，宜先短后长","ABD","2021\u002F2020版教材P57页 沉桩顺序：对于密集桩群，自中间向两个方向或四周对称施打；根据基础的设计高程，宜先深后浅；根据桩的规格，宜先大后小，先长后短。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]