[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126931":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1126931,792,2,"多选题","关于沉入桩施工技术要点，正确的有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","沉桩时，桩锤、桩帽或送桩帽应和桩身在同一中心线上",true,{"key":16,"text":17,"correct":18},"B","桩身垂直度偏差不得超过1%",false,{"key":20,"text":21,"correct":14},"C","接桩可采用焊接、法兰连接或机械连接",{"key":23,"text":24,"correct":14},"D","终止锤击应以控制桩端设计高程为主，贯入度为辅",{"key":26,"text":27,"correct":14},"E","沉桩过程中应加强对邻近建筑物、地下管线等的观测、监护","ACDE","2021\u002F2020版教材P57页 沉入桩施工时预制桩的接桩可采用焊接、法兰连接或机械连接，接桩材料工艺应符合规范要求；沉桩时，桩帽或送桩帽与桩周围间隙应为5---10mm；桩锤、桩帽或送桩帽应和桩身在同一中心线上；桩身垂直度偏差不得超过0.5%。终止锤击的控制应以控制桩端设计高程为主，贯入度为辅；沉桩过程中应加强临近建筑物、地下管线等的检测、监护。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]