[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126913":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1126913,792,2,"多选题","下列先张法预应力张拉施工规定中，正确的有( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","张拉台座应具有足够的强度和刚度",true,{"key":16,"text":17,"correct":14},"B","锚板受力中心应与预应力筋合力中心一致",{"key":19,"text":20,"correct":21},"C","同时张拉多根预应力筋时，各根预应力筋的初始应力差值不得大于5%",false,{"key":23,"text":24,"correct":14},"D","预应力筋就位后，严禁使用电弧焊对梁体钢筋及模板进行切割或焊接",{"key":26,"text":27,"correct":14},"E","设计未规定时，应分阶段、对称、交错地放张","ABDE","2021\u002F2020版教材P45页 先张法预应力施工：（1）张拉台座应具有足够的强度和刚度。锚板受力中心应与预应力筋合力中心一致（2）就位后严禁使用电弧焊对梁体钢筋及模板进行切割或焊接（3）同时张拉多根预应力筋时，各根预应力筋的初始应力应一致（4）张拉顺序应符合设计要求，设计未规定时，应分阶段、对称、交错地放张。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]