[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126882":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1126882,792,2,"多选题","关于模板搭设、拆除要求，正确的有( )。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","安装模板应与钢筋工序配合进行",true,{"key":16,"text":17,"correct":14},"B","安装墩、台模板时，其底部应与基础预埋件连接牢固，上部应采用拉杆固定",{"key":19,"text":20,"correct":14},"C","模板在安装过程中，必须设置防倾覆设施",{"key":22,"text":23,"correct":14},"D","预应力混凝土结构的底模应在结构建立预应力后拆除",{"key":25,"text":26,"correct":27},"E","拆除非承重侧模应在混凝土强度达到2MPa以上",false,"ABCD","2021\u002F2020版教材P36~37页 安装模板应与钢筋工序配合进行，妨碍捆扎钢筋的模板，应待钢筋工序结束后再安装；安装墩、台模板时，其底部应与基层预埋件连接牢固，上部应采用拉杆固定；模板在安装工程中，必须设置防倾覆措施。非承重侧模应在混凝土强度能保证结构棱角不损坏时方可拆除，混凝土宜为2.5MPa及以上。预应力混凝土结构的侧模应在预应力张拉前拆除；底模应在结构建立预应力后拆除.。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]