[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126872":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1126872,792,2,"多选题","工程量清单计价是投标人完成招标人提供的拟建工程项目的工程量清单内容所需要的全部费用，包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","分部分项工程费",true,{"key":16,"text":17,"correct":14},"B","措施项目费",{"key":19,"text":20,"correct":21},"C","直接工程费",false,{"key":23,"text":24,"correct":14},"D","规费",{"key":26,"text":27,"correct":14},"E","税金","ABDE","工程量清单计价是投标人完成招标人提供的拟建工程项目的工程量清单内容所需要的全部费用，包括分部分项工程费、措施项目费、其他项目费和规费以及税金。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]