[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126849":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1126849,792,2,"多选题","进出工作井的安全质量控制主要措施有（）等。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","按照设计要求，采取超前小导管注浆加固措施",true,{"key":16,"text":17,"correct":14},"B","在进出位置安放钢拱架并及时喷射混凝土",{"key":19,"text":20,"correct":14},"C","根据设计给定的暗挖施工步骤，凿除进出位置的工作井支护结构",{"key":22,"text":23,"correct":24},"D","监测数据信息反馈，调整设计和施工参数",false,{"key":26,"text":27,"correct":14},"E","按照设计要求，采取大管棚注浆加固措施","ABCE","P277-279 进出工作井的安全质量控制主要措施： (1)按照设计要求,采取大管棚或者超前小导管注浆加固措施。 (2)根据设计给定的暗挖施工步骤,凿除进出位置的工作井支护结构。 (3)在进出位置安放钢拱架并及时喷射混凝土。 减少地面沉降措施： (1)依据监测数据信息反馈，调整设计和施工参数，保证沉降值控制在允许范围。 (2)根据实际情况采取地面预注浆、隧道内小导管注浆和衬砌结构背后注浆等措施，控制地层变形在允许范围。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]