[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126848":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1126848,792,2,"多选题","明挖法施工质量控制与验收包括（）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","基坑开挖施工",true,{"key":16,"text":17,"correct":14},"B","结构施工",{"key":19,"text":20,"correct":14},"C","基坑回填",{"key":22,"text":23,"correct":14},"D","主体结构防水施工",{"key":25,"text":26,"correct":27},"E","管线处理",false,"ABCD","P275-277 明挖法施工质量控制与验收有： （1）基坑开挖施工； （2）结构施工； （3）基坑回填； （4）主体结构防水施工； （5）特殊部位防水处理。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]