[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126847":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1126847,792,2,"多选题","钻孔灌注桩施工时，造成钻孔垂直度不符合规范要求的主要原因有（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","钻机安装不平整或钻进过程中发生不均匀沉降",true,{"key":16,"text":17,"correct":18},"B","未在钻杆上加设扶正器",false,{"key":20,"text":21,"correct":14},"C","钻杆弯曲、钻杆接头间隙太大",{"key":23,"text":24,"correct":14},"D","钻头翼板磨损不一，钻头受力不均",{"key":26,"text":27,"correct":14},"E","钻进中遇软硬土层交界面或倾斜岩面时，钻压过高使钻头受力不均","ACDE","P267-270 钻孔垂直度不符合规范要求的主要原因： (1)场地平整度和密实度差，钻机安装不平整或钻进过程发生不均匀沉降，导致钻孔偏斜。 (2)钻杆弯曲、钻杆接头间隙太大，造成钻孔偏斜。 (3)钻头翼板磨损不一，钻头受力不均，造成偏离钻进方向。 (4)钻进中遇到软硬土层交界面或倾斜岩面时，钻压过高使钻头受力不均，造成偏离钻进方向。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]