[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126841":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1126841,792,2,"多选题","管道回填做法错误的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","管道两侧和管顶以上500mm范围内的回填材料，应由沟槽两侧对称运入槽内",false,{"key":16,"text":17,"correct":18},"B","需要拌合的回填材料，应在在槽内拌合均匀",true,{"key":20,"text":21,"correct":18},"C","管基有效支承角范围应采用中粗砂或土填充密实，与管壁紧密接触",{"key":23,"text":24,"correct":18},"D","管道回填时间宜在一昼夜中气温最高时段，从管道两侧同时回填，同时夯实",{"key":26,"text":27,"correct":14},"E","管道回填从管底基础部位开始到管顶以上500mm范围内，必须采用人工回填","BCD","管道两侧和管顶以上500mm范围内的回填材料，应由沟槽两侧对称运入槽内，不得直接扔在管道上；回填其他部位时，应均匀运人槽内，不得集中推入。需要拌合的回填材料，应在运入槽内前拌合均匀，不得在槽内拌合。管基有效支承角范围应采用中粗砂填充密实，与管壁紧密接触，不得用土或其他材料填充。管道回填时间宜在一昼夜中气温最低时段，从管道两侧同时回填，同时夯实。管道回填从管底基础部位开始到管顶以上500mm范围内，必须采用人工回填；管顶500mm以上部位，可用机械从管道轴线两侧同时夯实；每层回填高度应不大于200mm。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]