[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126839":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1126839,792,2,"多选题","关于预应力施工的说法，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","承担预应力施工的单位应具有相应的施工资质",true,{"key":16,"text":17,"correct":18},"B","张拉设备的校准期限不得超过1年，且不得超过300次张拉作业",false,{"key":20,"text":21,"correct":18},"C","预应力张拉应由技术员主持",{"key":23,"text":24,"correct":18},"D","锚固完毕经检验合格后，方可使用电弧焊切割端头多余的预应力筋",{"key":26,"text":27,"correct":14},"E","封锚混凝土强度不宜低于结构混凝土强度等级的80%，且不得低于30MPa","AE","锚固完毕经检验合格后，方可切割端头多余的预应力筋，严禁使用电弧焊切割。张拉设备的校准期限不得超过半年，且不得超过200次张拉作业。预应力张拉应由项目技术负责人主持。故正确答案为AE。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]