[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126836":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1126836,792,2,"多选题","施工进度计划在实施过程中要进行必要的调整，调整内容包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","起止时间",true,{"key":16,"text":17,"correct":18},"B","网络计划图",false,{"key":20,"text":21,"correct":14},"C","持续时间",{"key":23,"text":24,"correct":14},"D","工作关系",{"key":26,"text":27,"correct":14},"E","资源供应","ACDE","施工进度计划调整内容应包括：工程量、起止时间、持续时间、工作关系、资源供应。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]