[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126824":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1126824,792,2,"多选题","根据《危险性较大的分部分项工程安全管理办法》，下列分部分项工程中，需要专家论证的有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","顶管工程",true,{"key":16,"text":17,"correct":14},"B","滑模模板工程",{"key":19,"text":20,"correct":14},"C","6m深的基坑工程",{"key":22,"text":23,"correct":24},"D","15m深的人工挖孔桩工程",false,{"key":26,"text":27,"correct":24},"E","最大起重量为250kN的龙门吊安装工程","ABC","超过一定规模的危险性较大的分部分项工程，应制定专项施工方案，通过专家论证。包括：（1）开挖深度超过 5m（含 5m）的基坑开挖、支护、降水工程；（2）滑模、爬模、飞模、隧道模工程；（3）采用矿山法、盾构法、顶管法施工的隧道、洞室工程；（4）开挖深度16m及以上的人工挖孔桩工程；（5）起重量300kN及以上的起重设备安装工程。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]