[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126823":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1126823,792,2,"多选题","关于施工成本管理措施，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","加强预测",false,{"key":16,"text":17,"correct":18},"B","加强定额和预算管理",true,{"key":20,"text":21,"correct":18},"C","完善原始记录和统计工作",{"key":23,"text":24,"correct":18},"D","建立考核和激励机制",{"key":26,"text":27,"correct":18},"E","建立健全责任制度","BCDE","为做好施工成本管理工作，必须做好以下工作： 1）加强成本管理观念； 2）加强定额和预算管理； 3）完善原始记录和统计工作； 4）建立健全责任制度； 5）建立考核和激励机制。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]