[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126821":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1126821,792,2,"多选题","索赔台账应反映（ ）内容。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","索赔发生原因",true,{"key":16,"text":17,"correct":14},"B","索赔意向提交时间",{"key":19,"text":20,"correct":21},"C","各种记录",false,{"key":23,"text":24,"correct":14},"D","监理审核结果",{"key":26,"text":27,"correct":21},"E","总包方审批结果","ABD","本题考查的是施工合同索赔。索赔台账应反映索赔发生的原因，索赔发生的时间、索赔意向提交时间、索赔结束时间，索赔申请工期和费用，监理工程师审核结果，发包方审批结果等内容。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]