[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126818":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1126818,792,2,"多选题","合同风险的分散和转移有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","减少承包方资金投入",false,{"key":16,"text":17,"correct":18},"B","向保险公司投保",true,{"key":20,"text":21,"correct":14},"C","加强索赔管理",{"key":23,"text":24,"correct":14},"D","加强成本控制",{"key":26,"text":27,"correct":18},"E","向分包商转移部分风险","BE","风险的分散和转移：1）向保险公司投保；2）向分包商转移部分风险。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]