[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126810":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1126810,792,2,"多选题","隧道工程开工前，应调查（ ）等资料并制订保护措施。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","机械设备情况",false,{"key":16,"text":17,"correct":14},"B","岩体类别",{"key":19,"text":20,"correct":21},"C","沿线地下管线",true,{"key":23,"text":24,"correct":21},"D","各构筑物",{"key":26,"text":27,"correct":21},"E","地面建筑物基础","CDE","工程开工前，应核对地质资料，调查沿线地下管线、各构筑物及地面建筑物基础等，并制订保护措施。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]