[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126801":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1126801,792,2,"多选题","因工程建设需要挖掘城镇道路的，应到（ ）办理审批手续，方可按照规定挖掘。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","公安部",false,{"key":16,"text":17,"correct":14},"B","绿化管理部门",{"key":19,"text":20,"correct":21},"C","市政工程行政主管部门",true,{"key":23,"text":24,"correct":21},"D","公安交通管理部门",{"key":26,"text":27,"correct":14},"E","道路管理部门","CD","因工程建设需要挖掘城镇道路的，应当持城镇规划部门批准签发的文件和有关设计文件，到市政工程行政主管部门和公安交通管理部门办理审批手续，方可按照规定挖掘。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]