[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126784":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1126784,792,2,"多选题","阶段性监测报告的内容应包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","天气情况",false,{"key":16,"text":17,"correct":18},"B","等值线图",true,{"key":20,"text":21,"correct":18},"C","施工进度",{"key":23,"text":24,"correct":18},"D","时程曲线",{"key":26,"text":27,"correct":14},"E","控制值","BCD","本题考查的内容是监控量测报告。阶段性监控量测报告应包括的内容：（1）工程概况及施工进度；（2）现场巡查信息；（3）监测数据图表：监测项目的累计变化值、变化速率值、时程曲线、必要的断面曲线图、等值线图、监测点平面位置图等；（4）监测数据、巡查信息的分析与说明；（5）结论与建议。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]