[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126759":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1126759,792,2,"多选题","关于石灰稳定土基层与水泥稳定土基层施工技术，下列叙述正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","宜用强制式拌合机进行拌合，拌合应均匀",true,{"key":16,"text":17,"correct":18},"B","宜在气温高于10℃进行施工，不宜冬期施工",false,{"key":20,"text":21,"correct":14},"C","摊铺好的稳定土类混合料应当天碾压成活",{"key":23,"text":24,"correct":18},"D","降雨时应停止施工，已摊铺的应覆盖土工织物防水",{"key":26,"text":27,"correct":14},"E","养护期内应封闭交通","ACE","选项B，宜在春末和气温较高季节施工，施工最低气温为5℃。选项D，雨期施工应防止石灰、水泥和混合料淋雨；降雨时应停止施工，已摊铺的应尽快碾压密实。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]