[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126738":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1126738,792,2,"多选题","有条件时，土基压实应做试验段，以取得（ ）等施工参数。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","碾压遍数",true,{"key":16,"text":17,"correct":14},"B","碾压机具组合",{"key":19,"text":20,"correct":21},"C","摊铺长度",false,{"key":23,"text":24,"correct":14},"D","路基预沉量值",{"key":26,"text":27,"correct":14},"E","每层虚铺厚度","ABDE","在正式进行路基压实前，有条件时应做试验段，以便取得路基施工相关的技术参数。试验目的主要有： 1）确定路基预沉量值； 2）合理选用压实机具；选用机具考虑因素有道路不同等级、工程量大小、施工条件和工期要求等。 3）按压实度要求，确定压实遍数。 4）确定路基宽度内每层虚铺厚度。 5）根据土的类型、湿度、设备及场地条件，选择压实方式。故选ABDE",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]