[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126735":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1126735,792,2,"多选题","在路基压实施工中，路基压实的方式有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","超重力压实",false,{"key":16,"text":17,"correct":18},"B","重力压实",true,{"key":20,"text":21,"correct":18},"C","振动压实",{"key":23,"text":24,"correct":14},"D","人工夯实",{"key":26,"text":27,"correct":14},"E","机械夯实","BC","本题考查的是路基材料与填筑、压实施工要点。压实方法：重力压实（静压）和振动压实两种。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]