[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126727":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1126727,792,2,"多选题","土工合成材料膨润土垫（GCL）铺设做法错误的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","进行GCL铺设作业，每一工作面施工前均要对基底进行修整和检验",false,{"key":16,"text":17,"correct":18},"B","对铺开的GCL进行调整，调整搭接宽度，控制在150±50mm范围内",true,{"key":20,"text":21,"correct":14},"C","拉平GCL，确保无褶皱、无悬空现象，与基础层贴实",{"key":23,"text":24,"correct":18},"D","GCL的搭接应采用下压上的搭接方式",{"key":26,"text":27,"correct":14},"E","注意避免出现十字搭接，应尽量采用品形分布","BD","质量控制要点：（1）填埋区基底检验合格，进行GCL铺设作业，每一工作面施工前均要对基底进行修整和检验。（2）对铺开的GCL进行调整，调整搭接宽度，控制在250±50mm范围内。拉平GCL，确保无褶皱、无悬空现象，与基础层贴实。（3）掀开搭接处上层GCL垫，在搭接处均匀撒膨润土粉，将两层垫间密封，然后将掀开的GCL铺回。（4）根据填埋区基底设计坡向，GCL的搭接应尽量采用顺坡搭接。即采用上压下的搭接方式；注意避免出现十字搭接，应尽量采用品形分布。（5）GCL须当日铺没当日覆盖，遇有雨雪天气应停止施工，并将已铺设的GCL覆盖好。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]