[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126702":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1126702,792,2,"多选题","供热站试运行要求有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","供热站在试运行前，站内所有系统和设备须经有关各方预验收合格",true,{"key":16,"text":17,"correct":14},"B","供热站在试运行前，供热管网与热用户系统已具备试运行条件",{"key":19,"text":20,"correct":14},"C","试运行的时间应为连续运行72h",{"key":22,"text":23,"correct":24},"D","试运行的时间应为连续运行36h",false,{"key":26,"text":27,"correct":14},"E","试运行应在设计的参数下进行","ABCE","本题考查的是供热管道试运行的规定。供热站在试运行前，站内所有系统和设备须经有关各方预验收合格，供热管网与热用户已具备试运行条件。试运行在建设单位、设计单位认可的参数下进行，试运行的时间应为连续运行72h。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]