[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126695":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1126695,792,2,"多选题","（ ）必须经严密性试验合格后方可投入运行。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","污水管道",true,{"key":16,"text":17,"correct":14},"B","雨污水合流管道",{"key":19,"text":20,"correct":14},"C","流砂地区雨水管道",{"key":22,"text":23,"correct":14},"D","膨胀土地区雨水管道",{"key":25,"text":26,"correct":27},"E","黏土地区雨水管道",false,"ABCD","本题考查的是给排水管道功能性试验基本规定。污水、雨污水合流管道及湿陷性土、膨胀土、流砂地区的雨水管道，必须经严密性试验合格后方可投入运行。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]