[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126689":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1126689,792,2,"多选题","关于给水排水压力管道水压试验的准备工作，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","管道未回填土且沟槽内无积水",false,{"key":16,"text":17,"correct":18},"B","应做好水源引接、排水等疏导方案",true,{"key":20,"text":21,"correct":18},"C","试验前应清除管道内的杂物",{"key":23,"text":24,"correct":18},"D","试验管段所有敞口应封闭，不得有渗漏水现象",{"key":26,"text":27,"correct":18},"E","试验管段不得用闸阀做堵板，不得含有消火栓、水锤消除器、安全阀等附件","BCDE","给水排水管道功能性试验分为压力管道的水压试验和无压管道的严密性试验。压力管道水压试验准备工作：试验管段所有敞口应封闭，不得有渗漏水现象；试验管段不得用闸阀作堵板，不得含有消火栓、水锤消除器、安全阀等附件；水压试验前应清除管道内的杂物；应做好水源引接、排水等疏导方案。A选项属于无压管道闭水试验的准备工作。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]