[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126682":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1126682,792,2,"多选题","关于现浇预应力钢筋混凝土水池的模板及支架拆除，下列说法中正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","应按模板支架设计方案、程序进行拆除",true,{"key":16,"text":17,"correct":18},"B","板、梁、拱、壳跨度≤8m，底模板应在结构强度≥75% 设计强度后拆除",false,{"key":20,"text":21,"correct":14},"C","板、梁、拱、壳跨度>8m，底模板应在结构强度≥100%设计强度后拆除",{"key":23,"text":24,"correct":14},"D","应在混凝土强度能保证其表面及棱角不因拆除模板而损坏时，拆除侧模板",{"key":26,"text":27,"correct":14},"E","模板及支架拆除时，应划定安全范围，设专人指挥和值守","ACDE","现浇预应力钢筋混凝土水池模板及支架拆除： （1）应按模板支架设计方案、程序进行拆除。 （2）采用整体模板时，侧模板应在混凝土强度能保证其表面及棱角不因拆除模板而受损坏时，方可拆除；底模板应在与结构同条件养护的混凝土试块达到表2K314021规定强度，方可拆除。 （3）模板及支架拆除时，应划定安全范围，设专人指挥和值守。故选ACDE。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]