[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126680":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1126680,792,2,"多选题","当构筑物无抗浮设计时，雨汛期水池施工中的抗浮措施有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","构筑物下及基坑内四周埋设排水盲管（盲沟）和抽水设备",true,{"key":16,"text":17,"correct":14},"B","基坑四周设防汛墙，防止外来水进入基坑",{"key":19,"text":20,"correct":14},"C","必要时放水进入构筑物，使构筑物内外无水位差",{"key":22,"text":23,"correct":24},"D","增加池体钢筋所占比例",false,{"key":26,"text":27,"correct":14},"E","备有应急供电和排水设施并保证其可靠性","ABCE","雨期施工时，施工中常采用的抗浮措施如下： 1）基坑四周设防汛墙，防止外来水进入基坑；建立防汛组织，强化防汛工作。 2）构筑物下及基坑内四周埋设排水盲管（盲沟）和抽水设备，一旦发生基坑内积水随即排除。 3）备有应急供电和排水设施并保证其可靠性。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]