[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126662":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1126662,792,2,"多选题","关于分节制作沉井的要求，正确的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","第一节制作高度必须高于刃脚部分",true,{"key":16,"text":17,"correct":14},"B","设计无要求时，前节混凝土强度应达到设计强度75%，方可浇筑后节混凝土",{"key":19,"text":20,"correct":21},"C","沉井每次接高时各部位的轴线位置应基本重合",false,{"key":23,"text":24,"correct":14},"D","混凝土施工缝处理应采用凹凸缝或设置钢板止水带，施工缝应凿毛并清理干净",{"key":26,"text":27,"correct":14},"E","分节制作.分次下沉的沉井严禁在接高施工过程中发生倾斜和突然下沉","ABDE","本题考查的是沉井的预制。选项C的正确说法“沉井每次接高时各部位的轴线位置应一致、重合，及时做好沉降和位移监测”。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]