[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126658":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1126658,792,2,"多选题","关于预制拼装给排水构筑物现浇板缝施工说法，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","板缝部位混凝土表面不用凿毛",false,{"key":16,"text":17,"correct":18},"B","外模应分段随浇随支",true,{"key":20,"text":21,"correct":18},"C","内模一次安装到位",{"key":23,"text":24,"correct":18},"D","宜采用微膨胀水泥",{"key":26,"text":27,"correct":14},"E","板缝混凝土应与壁板混凝土强度相同","BCD","本题考查的是装配式预应力钢筋混凝土水池施工技术。预制安装水池满水试验能否合格，除底板混凝土施工质量和预制混凝土壁板质量满足抗渗标准外，现浇壁板缝混凝土也是防渗漏的关键；必须控制其施工质量，具体操作要点如下：壁板接缝的内模宜一次安装到顶；外模应分段随浇随支。浇筑前，接缝的壁板表面应洒水保持湿润，模内应洁净；接缝的混凝土强度应符合设计规定，设计无要求时，应比壁板混凝土强度提高一级；用于接头或拼缝的混凝土或砂浆，宜采取微膨胀和快速水泥，在浇筑过程中应振捣密实并采取必要的养护措施。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]