[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126649":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1126649,792,2,"多选题","一般采用管棚超前支护的场合有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","隧道洞口段施工",true,{"key":16,"text":17,"correct":14},"B","通过断层破碎带等特殊地层",{"key":19,"text":20,"correct":21},"C","岩层较为坚硬的地段",false,{"key":23,"text":24,"correct":14},"D","修建大断面地下工程",{"key":26,"text":27,"correct":14},"E","穿越地下和地面结构物修建地下工程","ABDE","本题考查的是管棚施工技术。通常，在下列施工场合应考虑采用管棚进行超前支护： （1）穿越铁路修建地下工程； （2）穿越地下和地面结构物修建地下工程； （3）修建大断面地下工程； （4）隧道洞口段施工； （5）通过断层破碎带等特殊地层； （6）特殊地段，如大跨度地铁车站、重要文物保护区、河底、海底的地下工程施工等。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]