[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126639":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1126639,792,2,"多选题","喷锚暗挖（矿山）法施工隧道的复合式衬砌，防水控制重点部位包括（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","变形缝",true,{"key":16,"text":17,"correct":14},"B","施工缝",{"key":19,"text":20,"correct":14},"C","后浇带",{"key":22,"text":23,"correct":24},"D","预制件",false,{"key":26,"text":27,"correct":24},"E","桩身","ABC","本题考查的是隧道防水结构施工原则与方案选择。喷锚暗挖（矿山）法施工隧道通常采用复合式衬砌，以结构自防水为根本，辅以防水层组成防水体系，以变形缝、施工缝、后浇带、穿墙洞、预埋件、桩头等接缝部位混凝土及防水层施工为防水控制重点。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]