[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126637":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1126637,792,2,"多选题","当地层条件差、断面特大时，一般设计成多跨结构，跨与跨之间有梁、柱连接，可采用（ ）等施工。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","CRD法",false,{"key":16,"text":17,"correct":18},"B","中洞法",true,{"key":20,"text":21,"correct":18},"C","柱洞法",{"key":23,"text":24,"correct":14},"D","双侧壁导坑法",{"key":26,"text":27,"correct":18},"E","侧洞法","BCE","本题考查的是浅埋暗挖法掘进方式。当地层条件差、断面特大时，一般设计成多跨结构，跨与跨之间有梁、柱连接，可采用中洞法、侧洞法、柱洞法及洞桩法等施工。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]