[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126635":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1126635,792,2,"多选题","控制基坑底部土体过大隆起的方法有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","增加支撑刚度",false,{"key":16,"text":17,"correct":18},"B","增加围护结构入土深度",true,{"key":20,"text":21,"correct":18},"C","加固坑底土体",{"key":23,"text":24,"correct":18},"D","采取减压井降水",{"key":26,"text":27,"correct":18},"E","适时施作底板结构","BCDE","本题考查的是基坑的变形控制。坑底稳定控制：（1）保证深基坑坑底稳定的方法有加深围护结构入土深度、坑底土体加固、坑内井点降水等措施；（2）适时施作底板结构。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]