[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126608":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1126608,792,2,"多选题","关于盖挖施工车站结构，中间竖向临时支撑系统设置的方法有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","永久柱两侧单独设置临时柱",true,{"key":16,"text":17,"correct":18},"B","永久柱两侧单独设置永久柱",false,{"key":20,"text":21,"correct":14},"C","临时柱和永久柱合一",{"key":23,"text":24,"correct":14},"D","临时柱和永久柱合一，同时增设临时柱",{"key":26,"text":27,"correct":18},"E","临时柱和永久柱分离","ACD","本题考查的是不同方法施工的地铁车站结构。中间竖向临时支撑系统由临时立柱及其基础组成，系统的设置方法有三种：（1）在永久立柱的两侧单独设置临时柱；（2）临时柱与永久柱合一；（3）临时柱与永久柱合一，同时增设临时柱。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]