[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126604":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1126604,792,2,"多选题","浅埋暗挖法在进行隧道的设计和施工时，遵循的原则包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","管超前",true,{"key":16,"text":17,"correct":14},"B","严注浆",{"key":19,"text":20,"correct":21},"C","长开挖",false,{"key":23,"text":24,"correct":14},"D","强支护",{"key":26,"text":27,"correct":21},"E","慢封闭","ABD","本题考查的是地铁车站施工方法与选择条件。“十八字”原则：“管超前、严注浆、短开挖、强支护、快封闭、勤量测”。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]