[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126603":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1126603,792,2,"多选题","盾构法施工主要步骤包括（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","工作井建造",true,{"key":16,"text":17,"correct":14},"B","掘进出土",{"key":19,"text":20,"correct":14},"C","管片安装",{"key":22,"text":23,"correct":24},"D","地表注浆",false,{"key":26,"text":27,"correct":14},"E","衬砌背后注浆","ABCE","本题考查的是地铁区间隧道施工方法比较与选择。盾构法施工主要步骤为：（1）工作井建造；（2）盾构安装就位；（3）盾构从始发井推出；（4）出土并安装衬砌管片；（5）衬砌背后注浆；（6）盾构到达工作井并拆除。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]