[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126601":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1126601,792,2,"多选题","箱涵顶进前应检查验收（ ），必须符合要求。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","箱涵主体结构的混凝土强度",true,{"key":16,"text":17,"correct":14},"B","后背施工",{"key":19,"text":20,"correct":14},"C","顶进设备液压系统安装及预顶试验结果",{"key":22,"text":23,"correct":24},"D","侧墙刃脚切土状况",false,{"key":26,"text":27,"correct":14},"E","箱涵防水层及保护层","ABCE","箱涵顶进前检查工作：（1）箱涵主体结构混凝土强度必须达到设计强度，防水层及保护层按设计完成。（2）顶进作业面包括路基下地下水位已降至基底下500mm以下，并宜避开雨期施工，若在雨期施工，必须做好防洪及防雨排水工作。（3）后背施工、线路加固达到施工方案要求；顶进设备及施工机械符合要求。（4）顶进设备液压系统安装及预顶试验结果符合要求。（5）工作坑内与顶进无关人员、材料、物品及设施撤出现场。（6）所穿越的线路管理部门的配合人员、抢修设备、通信器材准备完毕。侧墙刃脚切土是在顶进挖土过程中。故选ABCE。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]