[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126592":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1126592,792,2,"多选题","关于现浇混凝土墩、台施工要求，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","重力式墩台混凝土浇筑前应对基础混凝土顶面做凿毛处理，清除锚筋污锈",true,{"key":16,"text":17,"correct":18},"B","重力式墩台混凝土宜水平分层浇筑，每层高度宜为2.5m",false,{"key":20,"text":21,"correct":14},"C","重力式墩台混凝土分块浇筑时，每块面积不得小于50m2",{"key":23,"text":24,"correct":14},"D","明挖基础上灌注墩.台第一层混凝土时，要防止水分被基础吸收",{"key":26,"text":27,"correct":18},"E","柱式墩台柱的混凝土宜分层分块浇筑","ACD","本题考查的是墩台和盖梁施工技术。重力式墩台混凝土宜水平分层浇筑，每层高度宜为1.5～2m；柱式墩台柱的混凝土宜一次连续浇筑完成。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]