[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126591":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1126591,792,2,"多选题","在一个基坑内沉入多根桩时，下列关于打桩顺序的说法中，正确的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","由一端向另一端打",true,{"key":16,"text":17,"correct":14},"B","密集群桩由中心向四边打",{"key":19,"text":20,"correct":21},"C","先打浅桩，后打深桩",false,{"key":23,"text":24,"correct":14},"D","先打靠近建筑物的桩，然后往外打",{"key":26,"text":27,"correct":21},"E","先打坡脚，后打坡顶","ABD","本题考查的是沉入桩基础。选项C的正确说法“先打深桩，后打浅桩”；选项E的正确说法“先打坡顶，后打坡脚”。沉桩顺序：对于密集桩群，自中间向两个方向或四周对称施打；根据基础的设计高程，宜先深后浅；根据桩的规格，宜先大后小，先长后短。",{"id":6,"name":31,"category":32,"favorite":33},"二建市政工程实务","建筑工程",0]