[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126554":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1126554,792,1,"单选题","某市政工程的网络计划图如下，其合理的合同工期应是()个月。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","6",false,{"key":16,"text":17,"correct":14},"B","8",{"key":19,"text":20,"correct":14},"C","9",{"key":22,"text":23,"correct":24},"D","10",true,"【考点】市政公用工程横道图和网络计划图的编制 对于本工程网络图，线路分别有：1―2―5―6；1―2―3―4―5―6；1―2―3―4―6;1―3―4―5―6；1―3―4―6。每条线路上工作的持续时间分别为：9、10、8、8、6。1―2―3―4―5―6持续时间最长，所以为关键线路。根据线路中最长的持续时间确定计算工期为10个月。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]