[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126553":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1126553,792,1,"单选题","假山的施工工艺流程为()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","放线挖槽→拉底→基础施工→扫缝→中层施工→收顶→检查→完形",false,{"key":16,"text":17,"correct":14},"B","放线挖槽→基础施工→拉底→中层施工→扫缝→检查→收顶→完形",{"key":19,"text":20,"correct":14},"C","放线挖槽→拉底→基础施工→中层施工→扫缝→收顶→检查→完形",{"key":22,"text":23,"correct":24},"D","放线挖槽→基础施工→拉底→中层施工→扫缝→收顶→检查→完形",true,"【考点】假山施工的工艺流程。 假山施工要自上而下、自后向前、有主及次、分层进行，确保稳定实用。其流程：放线挖槽→基础施工→拉底→中层施工→扫缝→收顶→检查→完形。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]