[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126551":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1126551,792,1,"单选题","沉井施工铺垫木时，以n表示垫木根数，以Q表示第一节沉井重量，L和b表示垫木的长和宽，[σ]表示基底土容许承压力，则垫木根数计算公式为()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","n=2Q\u002F(Lb[σ])",false,{"key":16,"text":17,"correct":18},"B","n=Q\u002F(Lb[σ])",true,{"key":20,"text":21,"correct":14},"C","n=Q\u002F(2Lb[σ])",{"key":23,"text":24,"correct":14},"D","n=Q\u002F(3Lb[σ])","【考点】沉井垫木根数的计算。 沉井刃脚下应满铺垫木。一般常使用长短两种垫木相间布置，在刃脚的直线段应垂直铺设，圆弧部分应径向铺设。垫木的数量按垫木底面承压应力不大于0.1MPa,按n=Q\u002F（Lb[σ]）求算所需数量。实际排列时应对称铺设，故实际数量比计算结果应适当增加。刃脚下底模应按拆除的次序布置，预先断开。已删内容。不要求掌握。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]