[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126528":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1126528,792,1,"单选题","排水管道开槽埋管工序包括：①沟槽支撑与沟槽开挖、②砌筑检查井及雨水口、③施工排水和管道基础、④稳管、⑤下管、⑥接口施工、⑦沟槽回填、⑧管道安装质量检查与验收，正确的施工工艺排序是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","②→①→⑤→④→③→⑥→⑦→⑧",false,{"key":16,"text":17,"correct":14},"B","①→②→③→④→⑤→⑥→⑦→⑧",{"key":19,"text":20,"correct":14},"C","②→①→③→④→⑤→⑥→⑧→⑦",{"key":22,"text":23,"correct":24},"D","①→③→⑤→④→⑥→②→⑧→⑦",true,"【考点】开槽埋管施工技术要求 本题考核的是排水管道开槽埋管的正确工序。由于工序比较复杂，选项做了合并，但需要排序的仍然很多。不过，由于②砌筑检查井及雨水口不可能排在第一位，可以很容易排除A和C。②也不可能排在很前面，所以，正确的答案是D。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]